The following set of seven jobs is to be processed through two work centres at George Heinrich's printing company. The s

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The following set of seven jobs is to be processed through two work centres at George Heinrich's printing company. The s

Post by answerhappygod »

The Following Set Of Seven Jobs Is To Be Processed Through Two Work Centres At George Heinrich S Printing Company The S 1
The Following Set Of Seven Jobs Is To Be Processed Through Two Work Centres At George Heinrich S Printing Company The S 1 (14.02 KiB) Viewed 113 times
The following set of seven jobs is to be processed through two work centres at George Heinrich's printing company. The sequence is first printing, then binding Processing time at each of the work centres is shown in the following table: Printing (hours) 4 Binding (hours) 8 10 5 3 11 Job T U V w х Y Z 14 14 1 6 7 9 12 2
a) Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order 1 2 3 5
c) For the schedule developed using Johnson's rule, the total length of time taken to complete the seven printing and binding jobs is hours (enter your response as a whole number). d) The idle time in the binding shop based on the sequence developed using Johnson's rule is hour(s) (enter your response as a whole number). e) By splitting the first Job in half, the binding machine's idle time would be cut by hour(s) (enter your response rounded to one decimal place).