1. [-/20 Points] DETAILS ASWMSCI15 9.E.014. ASK YOUR TEACHER PRACTICE ANOTHER Davison Construction Company is buliding a

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

1. [-/20 Points] DETAILS ASWMSCI15 9.E.014. ASK YOUR TEACHER PRACTICE ANOTHER Davison Construction Company is buliding a

Post by answerhappygod »

1 20 Points Details Aswmsci15 9 E 014 Ask Your Teacher Practice Another Davison Construction Company Is Buliding A 1
1 20 Points Details Aswmsci15 9 E 014 Ask Your Teacher Practice Another Davison Construction Company Is Buliding A 1 (24.4 KiB) Viewed 11 times
1 20 Points Details Aswmsci15 9 E 014 Ask Your Teacher Practice Another Davison Construction Company Is Buliding A 2
1 20 Points Details Aswmsci15 9 E 014 Ask Your Teacher Practice Another Davison Construction Company Is Buliding A 2 (23.73 KiB) Viewed 11 times
1 20 Points Details Aswmsci15 9 E 014 Ask Your Teacher Practice Another Davison Construction Company Is Buliding A 3
1 20 Points Details Aswmsci15 9 E 014 Ask Your Teacher Practice Another Davison Construction Company Is Buliding A 3 (19.47 KiB) Viewed 11 times
1. [-/20 Points] DETAILS ASWMSCI15 9.E.014. ASK YOUR TEACHER PRACTICE ANOTHER Davison Construction Company is buliding a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 46- week completion date requested by the owner. The Davison project manager prepared the following project network. Stat Estimates of the optimistic, most probable, and pessimistic times On weeks) for the activities are as follows Activity Optimistic Most Probable Pessimistic 4 A 8 C D E F G P 6 6 3 6 S 10 5 6 7 12 S 9 " 15 6 12 " 18 7 10 17 20 H 13 Fish MY NOTES
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Optimistic Most Probable Activity A C D E F G H 4 6 6 3 6 5 10 5 8 7 12 5 9 B 15 6 Pessimistic 12 8 18 7 (b) What is the expected project completion time (in weeks)? 18 17 20 13 (a) Find the critical path. (Enter your answers as a comma-separated list.) t (c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places) C (d) Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 59 weeks for this calculation. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places)
(a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks (c) Based only on the critical path, what is the estimated probability the project can be completed in 46 weeks as requested by the owner? (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places) (d) Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 59 weeks for this calculation. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) (e) What should the construction company tell the owner? (Enter your free-form answer using as many characters as necessary) This arewer has not been graded ye Need Help? Peet!!