- Russo Corporation Manufactured 21 000 Air Conditioners During November The Overhead Cost Allocation Base Is 32 50 Per 1 (27.78 KiB) Viewed 10 times
Russo Corporation manufactured 21,000 air conditioners during November. The overhead cost-allocation base is $32.50 per
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Russo Corporation manufactured 21,000 air conditioners during November. The overhead cost-allocation base is $32.50 per
Russo Corporation manufactured 21,000 air conditioners during November. The overhead cost-allocation base is $32.50 per machine-hour. The following variable overhead data pertain to November Production Machine - hours Variable overhead cost per machine-hour What is the total variable overhead variance? OA. $9,250.00 unfavorable B. $9,250.00 favorable C. $4,062.50 favorable. OO OD. $4,062.50 unfavorable Actual 21,000 units 10,375 hours $32.00 Budgeted 23,000 units 11,500 hours $32.50