You are completing a project network diagram with the following information. Task A takes 25 days and has no predecessor
Posted: Wed Jul 06, 2022 6:06 am
You are completing a project network diagram with the followinginformation. Task A takes 25 days and has no predecessors. Task Bhas a duration of 20 days and has A as its predecessor. Task C canstart when B starts and has a duration of 30 days. Task D can startas soon as B is completed, and has a duration of 10 days. Task Ehas a duration of 40 days and has C and D as its predecessors. Whatis the critical path duration for this network?
Group of answer choices
a. 95 days
b. 45 days
c. 55 days
d. 75 days
Group of answer choices
a. 95 days
b. 45 days
c. 55 days
d. 75 days