ou are analyzing a project that has a SPI of 0.4. If the PV is $10,000, and the AC is $5000, what is the CPI? Group of a

Posted: Wed Jul 06, 2022 6:06 am
by answerhappygod
ou are analyzing a project that has a SPI of 0.4. If the PV is$10,000, and the AC is $5000, what is the CPI?
Group of answer choices
a. 0.4
b. 0.6
c. 0.8
d. 1.0