ou are analyzing a project that has a SPI of 0.4. If the PV is $10,000, and the AC is $5000, what is the CPI? Group of a

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

ou are analyzing a project that has a SPI of 0.4. If the PV is $10,000, and the AC is $5000, what is the CPI? Group of a

Post by answerhappygod »

ou are analyzing a project that has a SPI of 0.4. If the PV is$10,000, and the AC is $5000, what is the CPI?
Group of answer choices
a. 0.4
b. 0.6
c. 0.8
d. 1.0
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!