The budget at completion for your project is $200,000. The CPI for your project is 1.25. The project has thus far spent

Posted: Wed Jul 06, 2022 6:06 am
by answerhappygod
The budget at completion for your project is $200,000. The CPIfor your project is 1.25. The project has thus far spent 20% of thebudget. What is the estimate to complete?
Group of answer choices
a. $100,000
b. $120,000
c. $140,000
d. $160,000