Your project's schedule performance index (SPI) is 0.9. Your earned value (EV) is $9000, and your actual cost (AC) is $9

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Your project's schedule performance index (SPI) is 0.9. Your earned value (EV) is $9000, and your actual cost (AC) is $9

Post by answerhappygod »

Your project's schedule performance index (SPI) is 0.9. Yourearned value (EV) is $9000, and your actual cost (AC) is $9,500.What is the planned value?
Group of answer choices
a. $10,000
b. $10,556
c. $8100
d. $8550