Your project's schedule performance index (SPI) is 0.9. Yourearned value (EV) is $9000, and your actual cost (AC) is $9,500.What is the planned value?
Group of answer choices
a. $10,000
b. $10,556
c. $8100
d. $8550
Your project's schedule performance index (SPI) is 0.9. Your earned value (EV) is $9000, and your actual cost (AC) is $9
-