The debits to Work in Process-Roasting Department for Morning Brew Coffee Company for August, together with information

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The debits to Work in Process-Roasting Department for Morning Brew Coffee Company for August, together with information

Post by answerhappygod »

The Debits To Work In Process Roasting Department For Morning Brew Coffee Company For August Together With Information 1
The Debits To Work In Process Roasting Department For Morning Brew Coffee Company For August Together With Information 1 (31.58 KiB) Viewed 24 times
The Debits To Work In Process Roasting Department For Morning Brew Coffee Company For August Together With Information 2
The Debits To Work In Process Roasting Department For Morning Brew Coffee Company For August Together With Information 2 (53.36 KiB) Viewed 24 times
The Debits To Work In Process Roasting Department For Morning Brew Coffee Company For August Together With Information 3
The Debits To Work In Process Roasting Department For Morning Brew Coffee Company For August Together With Information 3 (51.87 KiB) Viewed 24 times
The debits to Work in Process-Roasting Department for Morning Brew Coffee Company for August, together with information concerning production, are as follows: Work in process, August 1, 800 pounds, 30% completed. $4,084* Direct materials (800 x $4.70) Conversion (800 x 30% × $1.35) Coffee beans added during August, 16,343 pounds Conversion costs during August Work in process, August 31, 443 pounds, 42% completed Goods finished during August, 16,700 pounds. $3,760 324 $4,084 HIIHT 74,361 24,969 All direct materials are placed in process at the beginning of production. This information has been collected in the Microsoft Excel Online file. Open the spreadsheet, perform the required analysis, and input your answers in the questions below Open spreadsheet a. Prepare a cost of production report, presenting the following computations: 1. Direct materials and conversion equivalent units of production for August 2. Direct materials and conversion costs per equivalent unit for August 3. Cost of goods finished during August 4. Cost of work in process at August 31 7 If an amount is zero, enter "0". Round the answers in units to the nearest whole number, the answer for the cost per equivalent unit to the nearest cent, and the other monetary answers to the nearest whole dollar. Morning Brew Coffee Company
Morning Brew Coffee Company Cost of Production Report-Roasting Department For the Month Ended August 31 UNITS Units charged to production: Inventory in process, August 1 Received from materials storeroom Total units accounted for by the Roasting Department Units to be assigned costs: Inventory in process, August 1 Started and completed in August Transferred to finished goods in August Inventory in process, August 31 Total units to be assigned costs Check My Work COSTS Costs per equivalent unit: Total costs for August in Roasting Department Total equivalent units Cost per equivalent unit (2) Costs assigned to production: Whole Units Direct Materials: Equivalent Units Direct Materials (1) Costs Conversion Conversion (1) Total
COSTS Costs per equivalent unit: Total costs for August in Roasting Department Total equivalent units Cost per equivalent unit (2) Costs assigned to production: Inventory in process, August 1 O Costs incurred in August Total costs accounted for by the Roasting Department Costs allocated to completed and partially completed units: Inventory in process, August 1-balance To complete inventory in process, August 1 Cost of completed August 1 work in process. Started and completed in August Transferred to finished goods in August (3) Inventory in process, August 31 (4) Total costs assigned by the Roasting Department Change in direct materials cost per equivalent unit Change in conversion cost per equivalent unit Check My Work Materials. b. Compute and evaluate the change in cost per equivalent unit for direct materials and conversion from the previous month C cent. Increase or Decrease Conversion $ 0.0.0 Total Amount