6- The data about the assembly of a product is given as in the following table. It is desired: element Time (minutes) A
Posted: Tue Jul 05, 2022 11:41 am
6- The data about the assembly of a product is given as in the following table. It is desired: element Time (minutes) A B с D E F G H 3 2 2 2 2 5 4 1 First prerequisite A B D Ꭰ E C,G,F a. The cycle time (in minutes) if we desire to produce 24000 units of the product during one working year (each year is assumed to be 300 working days, each working day to be 8 hours) b. The number of stations and elements in each using RPW method c. The balance efficiency with two digits after the decimal