- Consider A Project With The Following Information Construct An Aon Diagram And Use The Two Pass Process Algorithm To Fi 1 (72.31 KiB) Viewed 11 times
Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to fi
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to fi
question. Activity A B C D E F G Immediate Predecessor A A B, C B D,E с
Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to find ES, EF, LS and LF for each activity. Activity Time (weeks) 3 5 7 3 6 4 2 8. Enter ES and LF of the following activities: ES of activity D is := 10 ES of activity F is := 8 LF of activity G is = 14 LF of activity C is = 11 9. Enter the slack of the following activities: The slack time for activity G is : 2 The slack time for activity E is = 0 10. The project length is := 11. What is (are) the critical path(s)? Enter 1, if your answer is A-B-E-F Enter 2, if your answer is A-B-D-F Enter 3, if your answer is A-C-D-F Enter 4, if your answer is A-B-D-F and A-C-G Enter 5, if your answer is A-B-E-F and A-C-G Answer: 1 Please answer all parts of the