Question 329 pts Product A MRP information is as below: Ordering cost = $250, inventory holding cost $2 per unit per wee
Posted: Sun Jul 03, 2022 5:22 pm
Question 329 pts
Product A MRP information is as below:
Ordering cost = $250, inventory holding cost $2 per unit per week. There are 120 units beginning inventory; there are no scheduled receipts at the beginning; EOQ = 122 units.
Hint:
Inventory carrying cost = Sum (cost per unit per week x ending inventory of a week )
Ordering cost = ordering cost per order x # of orders
Using EOQ method, what are your inventory carrying and ordering costs?
Group of answer choices
Carry = $920, Ordering = $540
Carry = $168, Ordering = $50
Carry = $724, Ordering = $500
Carry = $665, Ordering = $890
Carry = $425, Ordering = $1,215
Flag question: Question 33
Question 337 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Earliest Due Date rule.
Group of answer choices
AFT = 42.19, AL = 26.71, ANJ = 2.99
AFT = 15.4, AL = 23.8, ANJ = 1.29
AFT = 63.8, AL = 27.4, ANJ = 2.17
AFT = 32.9, AL = 31.12, ANJ = 3.01
AFT = 80.2, AL = 45.8, ANJ = 4.12
Flag question: Question 34
Question 347 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using First Come First Serve rule.
Group of answer choices
AFT = 70.4, AL = 34, ANJ = 2.39
AFT = 16.5, AL = 12, ANJ = 1.13
AFT = 34, AL = 16, ANJ = 3.49
AFT = 51, AL = 23, ANJ = 6.19
AFT = 100.5, AL = 42, ANJ = 5.41
Flag question: Question 35
Question 357 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Longest Processing Time rule.
Group of answer choices
AFT = 28.21, AL = 33.45, ANJ = 3.01
AFT = 12.81, AL = 21.43, ANJ = 2.16
AFT = 112.8, AL = 73.8, ANJ = 3.84
AFT = 46.83, AL = 58.37, ANJ = 3.13
AFT = 11.1, AL = 8.92, ANJ = 1.16
Product A MRP information is as below:
Ordering cost = $250, inventory holding cost $2 per unit per week. There are 120 units beginning inventory; there are no scheduled receipts at the beginning; EOQ = 122 units.
Hint:
Inventory carrying cost = Sum (cost per unit per week x ending inventory of a week )
Ordering cost = ordering cost per order x # of orders
Using EOQ method, what are your inventory carrying and ordering costs?
Group of answer choices
Carry = $920, Ordering = $540
Carry = $168, Ordering = $50
Carry = $724, Ordering = $500
Carry = $665, Ordering = $890
Carry = $425, Ordering = $1,215
Flag question: Question 33
Question 337 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Earliest Due Date rule.
Group of answer choices
AFT = 42.19, AL = 26.71, ANJ = 2.99
AFT = 15.4, AL = 23.8, ANJ = 1.29
AFT = 63.8, AL = 27.4, ANJ = 2.17
AFT = 32.9, AL = 31.12, ANJ = 3.01
AFT = 80.2, AL = 45.8, ANJ = 4.12
Flag question: Question 34
Question 347 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using First Come First Serve rule.
Group of answer choices
AFT = 70.4, AL = 34, ANJ = 2.39
AFT = 16.5, AL = 12, ANJ = 1.13
AFT = 34, AL = 16, ANJ = 3.49
AFT = 51, AL = 23, ANJ = 6.19
AFT = 100.5, AL = 42, ANJ = 5.41
Flag question: Question 35
Question 357 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Longest Processing Time rule.
Group of answer choices
AFT = 28.21, AL = 33.45, ANJ = 3.01
AFT = 12.81, AL = 21.43, ANJ = 2.16
AFT = 112.8, AL = 73.8, ANJ = 3.84
AFT = 46.83, AL = 58.37, ANJ = 3.13
AFT = 11.1, AL = 8.92, ANJ = 1.16