Question 329 pts Product A MRP information is as below: Ordering cost = $250, inventory holding cost $2 per unit per wee

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Question 329 pts Product A MRP information is as below: Ordering cost = $250, inventory holding cost $2 per unit per wee

Post by answerhappygod »

Question 329 pts
Product A MRP information is as below:
Ordering cost = $250, inventory holding cost $2 per unit per week. There are 120 units beginning inventory; there are no scheduled receipts at the beginning; EOQ = 122 units.
Hint:
Inventory carrying cost = Sum (cost per unit per week x ending inventory of a week )
Ordering cost = ordering cost per order x # of orders
Using EOQ method, what are your inventory carrying and ordering costs?
Group of answer choices
Carry = $920, Ordering = $540
Carry = $168, Ordering = $50
Carry = $724, Ordering = $500
Carry = $665, Ordering = $890
Carry = $425, Ordering = $1,215
Flag question: Question 33
Question 337 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Earliest Due Date rule.
Group of answer choices
AFT = 42.19, AL = 26.71, ANJ = 2.99
AFT = 15.4, AL = 23.8, ANJ = 1.29
AFT = 63.8, AL = 27.4, ANJ = 2.17
AFT = 32.9, AL = 31.12, ANJ = 3.01
AFT = 80.2, AL = 45.8, ANJ = 4.12
Flag question: Question 34
Question 347 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using First Come First Serve rule.
Group of answer choices
AFT = 70.4, AL = 34, ANJ = 2.39
AFT = 16.5, AL = 12, ANJ = 1.13
AFT = 34, AL = 16, ANJ = 3.49
AFT = 51, AL = 23, ANJ = 6.19
AFT = 100.5, AL = 42, ANJ = 5.41
Flag question: Question 35
Question 357 pts
A law office currently has five jobs to be scheduled, shown in the order in which they arrived.
Job
Processing Time (hours)
Due (hours)
V
13
24
W
12
35
X
50
46
Y
17
35
Z
55
63
Calculate Average Flow Time (Total flow time/# of jobs), Average Lateness (Total lateness / # of jobs) and Average Number of Jobs (Total flow time / Total processing time) by sequencing the tasks using Longest Processing Time rule.
Group of answer choices
AFT = 28.21, AL = 33.45, ANJ = 3.01
AFT = 12.81, AL = 21.43, ANJ = 2.16
AFT = 112.8, AL = 73.8, ANJ = 3.84
AFT = 46.83, AL = 58.37, ANJ = 3.13
AFT = 11.1, AL = 8.92, ANJ = 1.16