Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

A project consists of the following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A

Post by answerhappygod »

A project consists of the following activities. Times are givenin weeks.
Activity
Immediate Predecessor
Activity Time
A
--
3
B
--
2
C
--
3
D
A, B
3
E
B
5
F
C
1
G
D, E
4
H
F
4
5. What is (are) the critical path(s)?
Enter 1 if your answer is A-D-G
Enter 2 if your answer is B-D-G
Enter 3 if your answer is B-E-G
Enter 4 if your answer is A-B-E-G
Enter 5 if your answer is B-E-G and C-F-H
Answer :=_____
6. What is the project length? Answer:= ____
7. What is the slack of the shortest path?Answer:= ____