c) The two steps in preparing metal die are casting processes and precision machining. Personal fatigue and delay allowa
Posted: Sun Jul 03, 2022 3:18 pm
c) The two steps in preparing metal die are casting processes and precision machining. Personal fatigue and delay allowances are set at 15%. The casting machine operator is rated at 110% and the precision machinist is rated at 80%. Observed times per batch are given below in Table 3. Determine the standard time for the task. Discuss the result. Observed Time in Minutes 2 3 130 65 Table 3: Observed Times Per Batch 1 Task Casting Processes 120 Precision Machining 55 110 55 (5 Marks) 4 120 65 d) Discuss three (3) waste or "MUDA" that possibly can happen in Dayang Cast Sdn. Bhd. (6 Marks)