Using the priority list T3, T4, T7, T6, T5, T1, T2, schedule the project below with two processors. T1 (9) T2 (12) T3 (1
Posted: Fri Jul 01, 2022 9:09 am
Using the priority list T3, T4, T7, T6, T5, T1, T2, schedule the project below with two processors. T1 (9) T2 (12) T3 (10) T4 (5) T5 (6) T6 (4) T7 (3) End List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then T4 then T7, enter: 1,4,7. Ignore idle time.