- Using The Priority List T3 T4 T7 T6 T5 T1 T2 Schedule The Project Below With Two Processors T1 9 T2 12 T3 1 1 (52.1 KiB) Viewed 27 times
Using the priority list T3, T4, T7, T6, T5, T1, T2, schedule the project below with two processors. T1 (9) T2 (12) T3 (1
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Using the priority list T3, T4, T7, T6, T5, T1, T2, schedule the project below with two processors. T1 (9) T2 (12) T3 (1
Using the priority list T3, T4, T7, T6, T5, T1, T2, schedule the project below with two processors. T1 (9) T2 (12) T3 (10) T4 (5) T5 (6) T6 (4) T7 (3) End List the task numbers of the tasks processor one works on, in order. For example, if they work on T1 then T4 then T7, enter: 1,4,7. Ignore idle time.