The latest change request you received does not impact the project cost. As a Project Manager, what should be your next
Posted: Fri Jul 01, 2022 9:09 am
The latest change request you received does not impact the project cost. As a Project Manager, what should be your next step? O a. Send the Change Request to the Change Control Board (CCB) O b. Go ahead and make the change O c. Evaluate the impact on other project constraints O d. Speak to the Project Sponsor about the Change Request