The latest change request you received does not impact the project cost. As a Project Manager, what should be your next
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
The latest change request you received does not impact the project cost. As a Project Manager, what should be your next
The latest change request you received does not impact the project cost. As a Project Manager, what should be your next step? O a. Send the Change Request to the Change Control Board (CCB) O b. Go ahead and make the change O c. Evaluate the impact on other project constraints O d. Speak to the Project Sponsor about the Change Request