System unit: Lead Time=1 week; Minimum order quantity = 13,500 Week 1 2 3 4 Gross requirements 13,500 10,500 10,500 Sche
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
System unit: Lead Time=1 week; Minimum order quantity = 13,500 Week 1 2 3 4 Gross requirements 13,500 10,500 10,500 Sche
Each Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: Production plans for complete kits are as follows: Start assembling 13,500 kits in week 2 Start assembling 10,500 kits in weeks 3, 4, and 5 Start assembling 18,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 13,500 Week 1 2 3 Gross requirements 13,500 10,500 Scheduled receipts Projected ending inventory: 2,000 Net requirements Planned receipts ☐☐☐ 000 4 5 6 10,500 10,500 18,000 ☐☐☐ ☐☐☐