The next three questions (1-3) are based upon the following: Merrifield Post Office is evaluating the productivity of it

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The next three questions (1-3) are based upon the following: Merrifield Post Office is evaluating the productivity of it

Post by answerhappygod »

The next three questions (1-3) are based upon thefollowing:
Merrifield Post Office is evaluating the productivity of itsmail processing centers. The centers differ in the degree ofautomation, the type of work that can be performed and the skill ofthe workers.
Center
1
2
3
Pieces processed
1,000
2,000
3,000
Workers/hr
10
5
2
Hourly wage rate
$5.50
$10
$12
Overhead/hr
$10
$25
$50
[a] Calculate the multifactorproductivity if the new processing machine is installed.Show your work to get partial credits.
Short answer question: ShouldMerrifield install the new processing machine? (hint:consider productivity and other operations aspects that you believeshould be considered in this decision making).