3. If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15 weeks, $1,000 for 14 weeks, $900 for 1

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

3. If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15 weeks, $1,000 for 14 weeks, $900 for 1

Post by answerhappygod »

3 If The Indirect Costs For Each Duration Are 1 200 For 16 Weeks 1 130 For 15 Weeks 1 000 For 14 Weeks 900 For 1 1
3 If The Indirect Costs For Each Duration Are 1 200 For 16 Weeks 1 130 For 15 Weeks 1 000 For 14 Weeks 900 For 1 1 (10.69 KiB) Viewed 80 times
3 If The Indirect Costs For Each Duration Are 1 200 For 16 Weeks 1 130 For 15 Weeks 1 000 For 14 Weeks 900 For 1 2
3 If The Indirect Costs For Each Duration Are 1 200 For 16 Weeks 1 130 For 15 Weeks 1 000 For 14 Weeks 900 For 1 2 (23.38 KiB) Viewed 80 times
3. If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15 weeks, $1,000 for 14 weeks, $900 for 13 weeks, $860 for 12 weeks, $820 for 11 weeks, and $790 for 10 weeks, compute the total costs for each duration. Plot these costs on a graph. What is the optimum cost-time schedule?
Act. Crash Cost (Slope) 10 70 0 8 20 50 200 30 40 0 E Maximum Crash Time 0 2 3 3 1 A H Normal Time 4 7 1 4 5 5 2 2 2 Normal Cost 30 60 80 Total direct cost $ 40 110 90 60 70 140 $680 Time unit 1 week Project duration 16