3 If The Indirect Costs For Each Duration Are 1 200 For 16 Weeks 1 130 For 15 Weeks 1 000 For 14 Weeks 900 For 1 1 (10.69 KiB) Viewed 80 times
3 If The Indirect Costs For Each Duration Are 1 200 For 16 Weeks 1 130 For 15 Weeks 1 000 For 14 Weeks 900 For 1 2 (23.38 KiB) Viewed 80 times
3. If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15 weeks, $1,000 for 14 weeks, $900 for 13 weeks, $860 for 12 weeks, $820 for 11 weeks, and $790 for 10 weeks, compute the total costs for each duration. Plot these costs on a graph. What is the optimum cost-time schedule?
Act. Crash Cost (Slope) 10 70 0 8 20 50 200 30 40 0 E Maximum Crash Time 0 2 3 3 1 A H Normal Time 4 7 1 4 5 5 2 2 2 Normal Cost 30 60 80 Total direct cost $ 40 110 90 60 70 140 $680 Time unit 1 week Project duration 16
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!