Marks 16 Question no 02 What is the cheapest way of reducing the project duration to 8 days (if possible) and how? Also
Marks 16 Question no 02 What is the cheapest way of reducing the project duration to 8 days (if possible) and how? Also show the increase in project cost Activities A B C D E F G. H I J Immediate predecessor A B A E E,C G,D F I,H Duration (days) Normal 5 4 10 10 7 5 4 6 7 4 Crashing Page 1 of 2 2 6 3 6 3 2 3 3 Cost (days) Normal 15000 20000 35000 20000 10000 20000 (35000)- 35000 25000 12000 Crash 20400 35200 20700 14000 26000 44000 65000 29000 11₁