Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,080 per unit;
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,080 per unit;
company believes all of its estimates are accurate only to within ±15%. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? (Enter the answers in dollars, not millions of dollars, i.e. 1,234,567. Omit $ sign in your response.) Scenario Base Best Worst Units Sales Unit Price $ $ $ Variable Cost $ Fixed Costs $ $
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,080 per unit; variable costs = $860 per unit; fixed costs = $6.0 million; quantity = 114,000 units. Suppose the