Using the Per Unit method and symmetrical components calculateexpected fault current with the load bus shorted fora Line to Ground fault. All generators areoperating at rated voltage. Assume all transformers aredelta on the primary and grounded Y on thesecondary.
SBASE = 100MVA
中 G1 LINE 1 MAAA LINE 3 Asseum T3 w mm LOAD T4 LINE 2 LINE 4 1448m (G2) m T2
Using the Per Unit method and symmetrical components calculate expected fault current with the load bus shorted for a Li
-