14. The following four jobs must be processed through a three-machine flow shop. Job 1 2 3 4 A 4 2 6 3 Machine B2 3 5 4
Posted: Thu Jun 30, 2022 7:39 pm
14. The following four jobs must be processed through a three-machine flow shop. Job 1 2 3 4 A 4 2 6 3 Machine B2 3 5 4 C 6 7 6 8 Find the optimal sequencing of the jobs in order to minimize the makespan. What is the makespan at the optimal solution? Draw a Gantt chart illustrating your solution.