- 14 The Following Four Jobs Must Be Processed Through A Three Machine Flow Shop Job 1 2 3 4 A 4 2 6 3 Machine B2 3 5 4 1 (97.52 KiB) Viewed 38 times
14. The following four jobs must be processed through a three-machine flow shop. Job 1 2 3 4 A 4 2 6 3 Machine B2 3 5 4
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
14. The following four jobs must be processed through a three-machine flow shop. Job 1 2 3 4 A 4 2 6 3 Machine B2 3 5 4
14. The following four jobs must be processed through a three-machine flow shop. Job 1 2 3 4 A 4 2 6 3 Machine B2 3 5 4 C 6 7 6 8 Find the optimal sequencing of the jobs in order to minimize the makespan. What is the makespan at the optimal solution? Draw a Gantt chart illustrating your solution.