Problem 4 Form This Schedule Of Activities 1 Draw Aon Network Diagram 2 What Is The Expected Time To Complete The P 1 (13.8 KiB) Viewed 36 times
Problem 4 Form This Schedule Of Activities 1 Draw Aon Network Diagram 2 What Is The Expected Time To Complete The P 2 (13.43 KiB) Viewed 36 times
Problem 4) Form this schedule of activities, 1- Draw AON network diagram? 2. What is the expected time to complete the project? 20 3. What is the critical path activities? A 4- Calculate ES.EF.LS,LF, TF and FF for each activity?
E Activity Time Immediate predecessor А 6 B 3 с 9 A D 4 A E 2 B F 3 B G 5 CE H 7 DF
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!