Problem 4) Form this schedule of activities, 1- Draw AON network diagram? 2. What is the expected time to complete the project? 20 3. What is the critical path activities? A 4- Calculate ES.EF.LS,LF, TF and FF for each activity?
E Activity Time Immediate predecessor А 6 B 3 с 9 A D 4 A E 2 B F 3 B G 5 CE H 7 DF