eres project plan. Plan for Copies 'R' Us to Produce Brochures A and B Activity Start End Elapsed Number of Time Copies
Posted: Wed Mar 09, 2022 8:45 am
A. Determine the PV, EV, and AC for Brochure A through March 31. B. Determine the SV, CV, SPI, and CPI for the production of Brochure A through March 31. C. Determine the PV, EV, and AC for Brochure B through March 31. + D. Determine the SV, CV, SPI, and CPI for the production of Brochure B through March 31. E. Forecast the EAC for Brochure A. F. Forecast the EAC for Brochure B. G. Determine the overall status of your project by adding together the SV, the CV, and the updated EAC for Brochures A and B.-