Eres Project Plan Plan For Copies R Us To Produce Brochures A And B Activity Start End Elapsed Number Of Time Copies 1 (305.35 KiB) Viewed 47 times
eres project plan. Plan for Copies 'R' Us to Produce Brochures A and B Activity Start End Elapsed Number of Time Copies Brochure Jan May 5 months 500 А 1 31 Total Cost $100,000 4 months 1,000 $100,000 Brochure B Feb 1 May 31 Total $200,000 A quick glance reveals that you budgeted $200 a copy for Brochure A ($100,000 / 500 copies) and $100 a copy for Brochure B ($100,000 / 1,000 copies). Suppose it's the end of March, and you're three months into the project. Here's what has happened as of March 31: Project Status as of March 31 Activity Start Elapsed Number of Copies Total Time Produced Cost 3 months 150 $45,000 Brochure Jan А 1 2 months 600 $30,000 Brochure Feb B 1 Total $75,000
A. Determine the PV, EV, and AC for Brochure A through March 31. B. Determine the SV, CV, SPI, and CPI for the production of Brochure A through March 31. C. Determine the PV, EV, and AC for Brochure B through March 31. + D. Determine the SV, CV, SPI, and CPI for the production of Brochure B through March 31. E. Forecast the EAC for Brochure A. F. Forecast the EAC for Brochure B. G. Determine the overall status of your project by adding together the SV, the CV, and the updated EAC for Brochures A and B.-
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!