REVIEW b. Use a template jig, capable of producing 50 parts per hour and costing $75.00, in the pro- duction department,
Posted: Fri Mar 04, 2022 10:13 am
REVIEW b. Use a template jig, capable of producing 50 parts per hour and costing $75.00, in the pro- duction department, where an operator earns $14.00per hour. c. Use a duplex jig, which costs $120.00and can produce a part every 26 seconds, in the produc- tion department, where an operator earns $14.00 per hour. 2. Using the listed alternatives, prepare a compara- tive analysis for the following tooling problem: A total of 950 flange plates require four holes accu- rately drilled 90 degrees apart to mate with a con- nector valve. Which of the listed alternatives is the most economically desirable? a. Have a machinist who earns $20.00 per hour lay out and drill each part at a rate of 2 minutes per part 3. Assuming everything to be the same as in prob- lem 2, which alternative is the most economical for 135 parts?