Given the following activities and precedence, draw the CPM
diagram.
Activity Time (days) Preceding Activity
A 8 -
B 5 -
C 7 -
D 8 A
E 8 B
F 10 B
G 5 C
H 7 D, E
I 5 F, G, H
(a)What is the Critical Path?
(b)How long will it take to complete this Project
Given the following activities and precedence, draw the CPM diagram. Activity Time (days) Preceding Activity A 8 - B
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am