- Consider The Following Activity Normal Time Crash Time Normal Cost Crash Cost Predecessor A 4 3 2200 2600 B 2 1 2400 28 1 (16.9 KiB) Viewed 39 times
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 28
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 28
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 2800 С 3 3 500 500 D 8 4 2200 2600 A E 6 3 600 1200 B F 3 2 3600 4200 с G 4 2 1100 2000 DE What is the cost for crashing the project by 6 days? wa OWN NN WA