Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 28

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 28

Post by answerhappygod »

Consider The Following Activity Normal Time Crash Time Normal Cost Crash Cost Predecessor A 4 3 2200 2600 B 2 1 2400 28 1
Consider The Following Activity Normal Time Crash Time Normal Cost Crash Cost Predecessor A 4 3 2200 2600 B 2 1 2400 28 1 (16.9 KiB) Viewed 39 times
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 2800 С 3 3 500 500 D 8 4 2200 2600 A E 6 3 600 1200 B F 3 2 3600 4200 с G 4 2 1100 2000 DE What is the cost for crashing the project by 6 days? wa OWN NN WA