Shown below is a table telling the time needed for each of a number of tasks and which tasks must immediately precede th
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Shown below is a table telling the time needed for each of a number of tasks and which tasks must immediately precede th
Shown below is a table telling the time needed for each of a number of tasks and which tasks must immediately precede them. Make a PERT diagram for this problem, and determine the project time and critical path. Task Time Preceding Tasks 6 none B 9 A, D 10 B, 1 D 8 none E 9 B F 13 I G 5 C, E, F H 9 Ι 6 D, H COAL UT none