If an activity can be completed in 14 weeks at a cost of $3,300 instead of the normal time of 16 weeks at a cost of $2,3

Posted: Sat Feb 19, 2022 3:06 pm
by answerhappygod
If An Activity Can Be Completed In 14 Weeks At A Cost Of 3 300 Instead Of The Normal Time Of 16 Weeks At A Cost Of 2 3 1
If An Activity Can Be Completed In 14 Weeks At A Cost Of 3 300 Instead Of The Normal Time Of 16 Weeks At A Cost Of 2 3 1 (28.06 KiB) Viewed 66 times
If an activity can be completed in 14 weeks at a cost of $3,300 instead of the normal time of 16 weeks at a cost of $2,300, then the crash cost per week for the given activity is a. $93 b. $500 C. $33 d. $2,800