If an activity can be completed in 14 weeks at a cost of $3,300 instead of the normal time of 16 weeks at a cost of $2,3

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

If an activity can be completed in 14 weeks at a cost of $3,300 instead of the normal time of 16 weeks at a cost of $2,3

Post by answerhappygod »

If An Activity Can Be Completed In 14 Weeks At A Cost Of 3 300 Instead Of The Normal Time Of 16 Weeks At A Cost Of 2 3 1
If An Activity Can Be Completed In 14 Weeks At A Cost Of 3 300 Instead Of The Normal Time Of 16 Weeks At A Cost Of 2 3 1 (28.06 KiB) Viewed 65 times
If an activity can be completed in 14 weeks at a cost of $3,300 instead of the normal time of 16 weeks at a cost of $2,300, then the crash cost per week for the given activity is a. $93 b. $500 C. $33 d. $2,800