The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in we

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in we

Post by answerhappygod »

The following table lists the components needed to assemble an
end item, the manufacturing or purchase lead times (in weeks) for
typical lot sizes, amount on hand, and the direct components of
each item and, in brackets, the number of each component for each
parent.
a. Not available in Connect.

b. If 46 units of the end item are to be
assembled, how many additional units of B are needed? (You don’t
need to develop the MRP tables.)

Additional units ____


c. An order for 46 units of the end item is
scheduled to be shipped at the start of week 11. What is the latest
week that the components of the order can be started and the order
still be ready to ship on time? (You don’t need to develop the MRP
tables.)

The latest week ____