1. Describe your interpretations and conclusions,
if any, from the results and trends displayed?
2. What additional information, if any, would be helpful
in order to draw better conclusions?
Thousands Cumulative Cumulative Budget Cost Actual Cost Boardwalk Extension - Thousands of Dollars Cumulative Earned Value $600 Boardwalk Extension CBC CAC CEV $500 July 1 $50 $85 $75 Aug 2 $100 $165 $175 $400 Sep 3 $200 $255 $275 $300 Oct 4 $300 $335 $375 $475 Nov 5 $375 $440 $200 -CBC Dec 6 $435 $490 $535 $100 CAC .... CEV Jan 7 $495 Feb 8 $555 $0 1 2 3 6 7 8 4 5 Project Month
1. Describe your interpretations and conclusions, if any, from the results and trends displayed? 2. What additional info
-