1. Consider the activities, precedence requirements and time for a given project. Activity Time Predecessor(s) А 4 None

Posted: Sat Feb 19, 2022 3:06 pm
by answerhappygod
 1
1 (43.95 KiB) Viewed 89 times
1. Consider the activities, precedence requirements and time for a given project. Activity Time Predecessor(s) А 4 None B 3 None с 5 None D 7 A E 8 A.B F 6 с G 4 D H 3 E.F I 1 GH Answer the following questions: a. Construct the network for this project using activity on arrow (AOA) and determine the activity schedule. Use dummy activity as applicable .(Refer to the examples given in the PERT/CPM lecture ) b. Identify the critical path critical time to complete the project.