1. Consider the activities, precedence requirements and time for a given project. Activity Time Predecessor(s) А 4 None
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
1. Consider the activities, precedence requirements and time for a given project. Activity Time Predecessor(s) А 4 None
questions: a. Construct the network for this project using activity on arrow (AOA) and determine the activity schedule. Use dummy activity as applicable .(Refer to the examples given in the PERT/CPM lecture ) b. Identify the critical path critical time to complete the project.
1. Consider the activities, precedence requirements and time for a given project. Activity Time Predecessor(s) А 4 None B 3 None с 5 None D 7 A E 8 A.B F 6 с G 4 D H 3 E.F I 1 GH Answer the following