- Wer Sheets Following Is A 5 Job 3 Machine Flow Shop Problem If The Johnson S Algorithm Can Be Applicable To This Proble 1 (145.67 KiB) Viewed 38 times
wer Sheets Following is a 5 job 3 machine flow shop problem. If the Johnson's algorithm can be applicable to this proble
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
wer Sheets Following is a 5 job 3 machine flow shop problem. If the Johnson's algorithm can be applicable to this proble
wer Sheets Following is a 5 job 3 machine flow shop problem. If the Johnson's algorithm can be applicable to this problem, a) Find the optimal sequence and the corresponding makespan. b) Calculate the each machine's idle time. Job Processing time Machinel Machine2 Machine3 1 12 9 11 2 20 12 3 14 16 4 20 12 5 8 8 20 8 6 4 Once you upload files from your second device, click on Sync to check your submission