OPERATION 1 Clay Mixing INSPECTION OPERATION 2 Casting 4M OPERATION 8 Packaging 2M Store OPERATION 9 15M -10M- TOTAL :39

Posted: Thu Jun 09, 2022 4:03 pm
by answerhappygod
Operation 1 Clay Mixing Inspection Operation 2 Casting 4m Operation 8 Packaging 2m Store Operation 9 15m 10m Total 39 1
Operation 1 Clay Mixing Inspection Operation 2 Casting 4m Operation 8 Packaging 2m Store Operation 9 15m 10m Total 39 1 (33.24 KiB) Viewed 323 times
Figure 1
Operation 1 Clay Mixing Inspection Operation 2 Casting 4m Operation 8 Packaging 2m Store Operation 9 15m 10m Total 39 2
Operation 1 Clay Mixing Inspection Operation 2 Casting 4m Operation 8 Packaging 2m Store Operation 9 15m 10m Total 39 2 (35.6 KiB) Viewed 323 times
Figure 2
Explain in details about the layout improvement from
figure 1 to figure 2 and their benefits .

*specify the duration and distance
OPERATION 1 Clay Mixing INSPECTION OPERATION 2 Casting 4M OPERATION 8 Packaging 2M Store OPERATION 9 15M -10M- TOTAL :39MIN 5M OPERATION 3 Base cutting OPERATION 4 Semi-Finishing OPERATION 6 Dipping -6M- OPERATION 7 Firing 6M OPERATION 5 Blasting
OPERATION 1 Clay Mixing OPERATION 2 Casting -2M- OPERATION3 Base cutting 3M 3M 3M OPERATION 6 DIPPING OPERATION 5 Blasting OPERATION 4 Semi-Finishing -4M- Packaging OPERATION 8 OPERATION 7 Firing 2M INSPECTION 2M 3M Store OPERATION 9