- Seepage Takes Place Beneath The Concrete Dam Shown In Figure With A Cutoff Wall At The Upstream Permeability Of The Fin 1 (145.45 KiB) Viewed 42 times
Seepage takes place beneath the concrete dam shown in figure with a cutoff wall at the upstream. Permeability of the fin
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Seepage takes place beneath the concrete dam shown in figure with a cutoff wall at the upstream. Permeability of the fin
Seepage takes place beneath the concrete dam shown in figure with a cutoff wall at the upstream. Permeability of the fine sandy-silty soil beneath the dam is 5x10-4 cm/s. Calculate the pore pressure at point A shown in figure: 25 m & 6 m 1.75m Datum 3.5 m 20 m A 56.25 kPa O 100 kPa 153.28 kPa 10 kPa 10 m straturg