Q2 (10 ents) The figure shows the design hourly volume for a major intersection, using the Webster method, determine a s
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Q2 (10 ents) The figure shows the design hourly volume for a major intersection, using the Webster method, determine a s
Q2 (10 ents) The figure shows the design hourly volume for a major intersection, using the Webster method, determine a suitable signal timing for the intersection using the two phase system given that. Each approach has 2 lane groups Saturation flow 3700 for each lane S Yellow interval = 3 sec 1325 210 Lost time 3 sec per phase All red interval=0 sec Peak hour factors 0.95 C L = Eli+R GOOD LUCK 713 855 Dil 944326 12:15 418