The construction of a swimming pool required the tasks shown in the table below: Task Time (days) A Prepare the area for
Posted: Wed Jun 08, 2022 6:45 am
The construction of a swimming pool required the tasks shown in the table below: Task Time (days) A Prepare the area for the pool 1 B Mix the concrete 0.5 C Lay the concrete 1 D Let the concrete dry E Purchase the tiles for the pool F Tile the pool 1 ? G Let the tiles dry H Fill the pool with water a) Construct a precedence table by copying and pasting the table below, and fill in column 4 (last column) with the correct prerequisites. (5 marks) b) Use the illustration tool to draw a precedence network for this project. (7 marks) b) Identify the critical path for the project. (1 mark) c) Find the minimum completion time for the project. (1 mark) 2 1 2 Prerequisites ? ? ? ? ?