An activity has a planned duration of 10 days and a float of 5 days, after updating the schedule it was found that it ha
Posted: Wed Jun 08, 2022 6:39 am
An activity has a planned duration of 10 days and a float of 5 days, after updating the schedule it was found that it has started as scheduled, the elapsed duration is 7 days until the current data date and the remaining duration is 7 days. What could be the current float of the activity? (3/3 Points)