If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60

Posted: Mon Jun 06, 2022 6:27 am
by answerhappygod
If the indirect costs for each duration are $300 for 27 days,
$240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23
days, and $50 for 22 days, compute the direct, indirect, and total
costs for each duration. What is the optimum cost-time schedule?
The customer offers you $10 for every day you shorten the project
from your original network. Would you take it? If so for how many
days?
If The Indirect Costs For Each Duration Are 300 For 27 Days 240 For 26 Days 180 For 25 Days 120 For 24 Days 60 1
If The Indirect Costs For Each Duration Are 300 For 27 Days 240 For 26 Days 180 For 25 Days 120 For 24 Days 60 1 (44 KiB) Viewed 61 times
Act. A B C D E F amoa u t Crash Cost (slope) 80 30 40 50 100 30 A 10 B 8 C 8 5 Maximum Crash Time 2 D 8 11 E B 15 23 3 1 2 241 F 6 LL Normal Time 10 8 5156 Normal Cost 40 10 80 50 100 20 $300 Project duration 27 Total direct cost $300