If the indirect costs for each duration are $300 for 27 days,
$240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23
days, and $50 for 22 days, compute the direct, indirect, and total
costs for each duration. What is the optimum cost-time schedule?
The customer offers you $10 for every day you shorten the project
from your original network. Would you take it? If so for how many
days?
Act. A B C D E F amoa u t Crash Cost (slope) 80 30 40 50 100 30 A 10 B 8 C 8 5 Maximum Crash Time 2 D 8 11 E B 15 23 3 1 2 241 F 6 LL Normal Time 10 8 5156 Normal Cost 40 10 80 50 100 20 $300 Project duration 27 Total direct cost $300
If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!