You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for t
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for t
per day for your project. Also, suppose that the center must pay
$50 per day for a temporary room on day 14 or beyond. Find the
minimum-cost project schedule. Fill in the table below to show the
proper schedule (time for each activity after crashing) for
completing the project at minimum cost. (Enter your responses
as integers.)Determine the total cost for this project's
schedule.
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. O Activity Normal Cost ($) Normal Time (days) 0 Crash Time (days) Crash Cost ($) Immediate Predecessor(s) START 0 0 0 A 8 50 7 160 START B 6 40 3 280 START C 4 70 3 190 B D 10 20 8 100 A, C E 6 30 6 30 A, C F 10 80 6 600 B G 4 50 1 320 D H 7 60 6 90 E, F FINISH 0 0 0 0 G, H a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is days. (Enter your response as an integer.)