QUESTION TWO Develop a material requirements plan for component H. Lead times for the end item and each component except
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION TWO Develop a material requirements plan for component H. Lead times for the end item and each component except
QUESTION TWO Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items. A C B (2) E (4) D (2) H (3) E (2) K D (2) H (3) K